on 12-22-2010 8:56 AM
Hi ALL,
I have following question: is it possible to use employee hourly wage maintained in infotype 0008 to calculate project actual cost after time conformation instead of planned price for activity type maintained in KP26?
thanks in advance,
Denis
Answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Its No and Yes
No in standard, yes in Z ...
Just to give some direction, for planned costs..
there are two options:
1 you can write a batch job which updates the standard cost revenue rates (CRR), in this case, create Cost revenue rates same as BP and update them by batch job, assign the relative CRR to each BP
2 in Badi pick 0008 based on BP number (which is XX<8 digit PERNR>) derive PERNR based on central person
For actuals modify CAT7.
Niranjan
Edited by: Niranjan Dandekar on Dec 22, 2010 4:12 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
4 | |
4 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.