cancel
Showing results for 
Search instead for 
Did you mean: 

Using employee wage for project evaluation in cProjects

0 Kudos

Hi ALL,

I have following question: is it possible to use employee hourly wage maintained in infotype 0008 to calculate project actual cost after time conformation instead of planned price for activity type maintained in KP26?

thanks in advance,

Denis

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Answered

Former Member
0 Kudos

Its No and Yes

No in standard, yes in Z ...

Just to give some direction, for planned costs..

there are two options:

1 you can write a batch job which updates the standard cost revenue rates (CRR), in this case, create Cost revenue rates same as BP and update them by batch job, assign the relative CRR to each BP

2 in Badi pick 0008 based on BP number (which is XX<8 digit PERNR>) derive PERNR based on central person

For actuals modify CAT7.

Niranjan

Edited by: Niranjan Dandekar on Dec 22, 2010 4:12 PM