on 12-21-2010 4:53 PM
Hi,
how we split the delivery because of insufficient trans port, what are the configuration settings and how systems knows transportation is insufficient?
Hi
You can use the subsequent delivery split using VLSP transaction incase if you have restrictions of not shipping the
entire delivery quantity in one go.
Kind regards,
Ramana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
how systems knows transportation is insufficient?
Unless you maintain somewhere in SAP these details, it is not possible to achieve your requirement.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
What do you mean by Insufficient transport?
provide clear requirement.
Regards,
Reazuddin MD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Below i mention my exact requirement please find,
Shipping unit split is exemplified as follows: if you are loading a delivery and find that the available loading space in a means of transport is insufficient (the truck is smaller than planned or contains other deliveries), you need to split up the existing delivery into several deliveries. It is easy to perform this split with packed goods or shipping units. Instead of creating multiple deliveries, you can also use the delivery split function to reduce the quantity to be delivered and return the remaining quantity to the warehouse. All the delivery and billing documents are then created on the basis of the quantity actually loaded.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.