Hi Gurus
I have three condition types in the pricing procedure.
ZTA1 - Material Price
ZTA2 - 10% of material price (ZTA1)
ZTA3 - Interest Rate
Please help me with the config to have ZTA2 calculated as 10% of ZTA1 and value of ZTA3 calculated independently of ZTA2 & ZTA1. I shall cross check to find the problem.
Regards
Kumar
Hi,
Please try this:
1st of all configer the Condition Type ZTA2 -> Calculat.type 'A' % at V/06.
From To
10 ZTA1
20 ZTA2 10
Subtotal
For ZTA3 please elaborate what do you want to say.
Thank You,
RB.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Elaborate your issue with example
Say material price is Rs 100 ZAT1
You want ZAT2 should be 10 % of ZAT1 that is Rs 10
ZAT2 is Rs 10
Now tell us what should be the value of ZAT3 in this example
You are telling interest rate independent od ZAT1 and ZAT2 etc
What is that
How it is calculated
Give us a sample calculation
This can help us to provide you more inputs
AS suggested you need to use subtotal
Regards
Raja
Hi Raja
We have a requirement to maintain the annual interest rate in the pricing procedure for information purpose and with the ability to change the value periodically. In the example provided, I do not want the value of ZTA3 (Interest rate) to be based on neither ZTA1 nor ZTA2. I also need to create a condition type (monthly interest rate) whose value will be ZTA3/12.
Please help achieve this. I hope this is clear.
Best Regds
Kumar
Hi
Still Confusing yaa
ZTA3 - 5% - Annual Fees - Maintained by condition records so users can change periodically.
5 % should be calculated on what base?
I understand it is not on 100 (ZTA1) or 10 ( ZAT2 )
How can you say simply 5% fee?
In a transaction it needs to be applied on some base naa?
5 % on some base? That base only i am asking?
If you say discount is 20 % and in a sales order that 20 % is applied on some base that is On material price
Like that how you are calculating 5 %
On what you will calculate that 5%
How this issue handled in the present system
Regards
Raja
hi,
forget about condition type and SAP for a moment.
if principal amount is there then only the concept of interest comes into picture.
here you are saying that calculate interest with out principal amount.
like wise
in SAP also we need a base amount or principal amount on which interest is calculated.
please let me know that.
balajia
Then ZTA3 will requierd a access sequence with Table based on the fields (criteria) it need to trigger automatically.
Thank You,
RB.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
you can achieve this by assigning this to FROM and TO Steps.
step condition type from to
10 ZTA1 - Material Price - 100
20 ZTA2 - 10% of material price (ZTA1) - 10 10 20
30 ZTA3 - Interest Rate
what about interest rate calculation basing on ZTA1 or ZTA2.
please confirm
balajia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
forget about condition type and SAP for a moment.
if principal amount is there then only the concept of interest comes into picture.
here you are saying that calculate interest with out principal amount.
like wise
in SAP also we need a base amount or principal amount on which interest is calculated.
please let me know that.
balajia
User | Count |
---|---|
103 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.