on 12-21-2010 11:14 AM
Hello experts,
I'm a beginner in cProject. I would like to know the logic of actual start and end date of a project.
I know we can fill manually these dates for a task, but how does it fill for a project or a phase?
Even after releasing my project, fields ACTUALSTART and ACTUALFINISH of table CGPL_PROJECT are not getting filled.
Has anyone faced this problem?
Thanks.
hi
when you start entering the confirmation of tasks then only the actual start and actual end date will populate.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The cgpl_project is a application-indepandent table, which is used by cProject and other applications. As the application cProject does not support actual dates of project header and phase level, the two fields does not occurs in UI.
Either you can add user-fields, which fill the dates using your own logic or using the evaluation of cProject to get the dates of actual-start or actual finish.
Kind regards,
Zhenbo
User | Count |
---|---|
13 | |
6 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.