cancel
Showing results for 
Search instead for 
Did you mean: 

APO Planned Orders re-explosion in ECC

Former Member
0 Kudos

Hi All,

In ECC there are 10 operations in routing.

In APO only 3 Work Center are CIFed, so the PDS has only three operations.

When the APO planned order gets back to ECC, re-explosion is needed for the planned order to get other seven operations

Please guide if their is any standard process to carry out the re-explosion.

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi amlanapo,

Plz check whether the IM for the planned order is active or not. Whenever the planned order gets ciffed from APO to ECC planned order gets re-exploded automatically, If this is not happening then you have to apply a standard note in ECC side for re-explosion.

Check the Note: 86553

Regards

Sravan maturu

Former Member
0 Kudos

Hi Sravan, thanks for getting this cleared.

Answers (0)