Work Center Required on Selection Screen

Former Member
0 Kudos

Dear All,

My client has required work center as selection criteria on usage decision screen.

Thanks to all.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member188931
Active Contributor
0 Kudos

Dear,

Try to use the QE01, QE505, here maintain the required operation and work center and give the USage decision.

Please check and revert.

Thanks,

Hrishi

Former Member
0 Kudos

hi, thanks for reply, QE01 we can select individual lots on work center,not collective, i want collective selection of inspection lot of particular work center.

Could not under stand QE505 T.code?

Thanks

former_member42743
Active Contributor
0 Kudos

Can you use QE51n? Or QE71 if u use insp points.

FF

former_member188931
Active Contributor
0 Kudos

Hi,

Read it as as QE05, if for the collective use the QE51N, here enter the wrok cnter and execute, you will get all the inspction lots against the same work center.

Thanks,

Hrishi

lakshmi_prasad7
Contributor
0 Kudos

YOU CAN DEVELOP WORKCENTRE FIELD IN QA32 THEN U WILL SELECT WORK CENTRE AND THEN GIVE THE USAGE DECISION PERTICULAR WORK CENTRE USAGE DECISION