on 12-20-2010 5:28 AM
Dear All,
As per the project we need to give budget in 1st level only and through user status it will be carry forward to all the levels, but in project we have given budget in 2nd level and 3rd level WBSE by mistake, when we did return the budget it become value 0 in 2nd and 3rd level wbse, after that we tried to do PO it saying budget exceed coz of the value 0
kindly suggest how to remove the value 0 from this levels
Thanks & Regards,
Chanty
Hi
Deactivate availablilty control on the project. Use transaction CJBW, this transaction is project specific. Need to allocate budget again to correct WBS and then continue.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your reply,
Ya as you said i can deactivate the availability control to do PO but value 0 how should i delete or change from other WBSE
Coz they have given Supplement budget for 2nd and 3rd WBSE then they did return so it become 0 budget so now 2nd n 3rd wbse available budget is 0 now i need to remove that value 0
thank you,
Regards,
Chanty
inital budget was around 1cr in 2nd WBSE and they did supplement for sum amount in 1st level wbse and then they did return from 2nd level to 1st level for the same amount once it is return 1cr rs from 2nd to 1st level, still 2nd level showing 0 value
herre we used T.code cj30 and cj37 and cj38
Ok, now try the following,
goto CJ38 now enter -1cr(negative budget equal to initial budget return amount) for 2nd WBSE. Now go to CJ30 and remove the budget from 2nd level WBSE only save it. then run OPSX enter only 2nd level WBSE(dont enter Project definition or other WBSE) execute, this will remove the budget from 2nd Level WBSE and also the system status "BUDG" from 2nd level WBSE.