on 12-19-2010 5:43 AM
Hi,
We are transferring the production version(customized table) in R3 to APO using PDS.
Later on if we are making changes to the table, which is the best option to transfer the changes to APO.
Would T Code CURTO_CREATE suffice it, if then what is the procedure else what are the other options.
Advance thanks.....
Prash
Hi Prash,
CURTO_CREATE is the best choice but you can use CFM2 or report RIMODINI as well.
Regards,
Alexander