Hi,
I'm assigning components to cost activities using Stock item category with procurement type: PReq + Reservation for WBS Element.
The issue is that no commitment cost is appearing once the components purchase requisitions are created. Once I post good issue (through MIGO) only the difference between the planned cost and the purchase actual cost appears on the reports as an actual cost.
All this process is working fine with external activities (I'm not assigning components) the purchase requisition cost appears on the commitment reports and the complete actual cost appears once I pot good issue.
I don't know if it might be a account determination problem or it might be some wrong customization?
Thanks,
mforman
Edited by: mforman on Dec 17, 2010 2:46 PM
Hi,
To show material cost as commitment item once PR gets generated, this can be acheived by creating Cost element for all the inventory related G/L accounts which are used in defining in T:OBYC for account determination against the valuation class assigned in material master. out of these G/L accounts few are Balance sheet accounts and few are P&L accounts. For All balance sheet accounts (in OBYC) ask the CO consultant to create cost elements with cost element category as 90, for all P&L accounts with CE category as 1. Once they define the cost elements, Refresh the information database with T: code: CJEN. Then you can see the commitments generated against material components also. Commitments are not getting updated in your report as there are no cost elements for Balance sheet Accounts.
Thanks & Regards
kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Once I post good issue (through MIGO) only the difference between the planned cost and the purchase actual cost appears on the reports as an actual cost.
i just want to clarify what values appear in your report.? you mean if planned cost is 100 and purchase order amt is 90 and goods issue is 50, the report for actual cost is 100? (difference between planned cost and purchase actual cost?)
anyway i believe this may be due to current standard of SAP wherein PR's and PO's from reservations are not treated as project commitments since technically it is going first to stock (therefore charged to the company, not to the project) and becomes actual cost only upon goods issuance..
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
We've realize that if we create a PO (from ME21N) with account assignment Q (as the ones generated from the Project) the cost of it doesn't appear as Commitment. But if we create the PR with account assignment P the cost appears as commitment in the project reports.
Does this information clarifies anything?
Thanks
>
> Hi,
>
> We've realize that if we create a PO (from ME21N) with account assignment Q (as the ones generated from the Project) the cost of it doesn't appear as Commitment. But if we create the PR with account assignment P the cost appears as commitment in the project reports.
> Does this information clarifies anything?
>
> Thanks
Please ask your CO consultant to create Statistical Cost Element for the Inventory GLs.
PR of component and external activity are entirely different. Why dont you try with internal activity and assign the same components and see what happens when you create PR and GR for the component.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Perfect, I've checked on FSS0 tcode the G/L account of the PR and assigned a cost element and now the PR cost appears as commitment on the report.
But the component cost stills not appearing in the RemOrdPlan ammount, do you think this could have any relationship with the G/L Account issue?
thanks a lot
I'm using report S_ALR_87013533.
I've created a project in which I just assigned a component to a cost activity.
The project has not been released yet.
At the report there is only the value of the component on the Plan column, this value also appears on Available column. The rest have zero value.
Thanks for your time.