cancel
Showing results for 
Search instead for 
Did you mean: 

Error while manually linking WBS to cProject/tasks

Former Member
0 Kudos

Hello,

While manually linking WBS to cProject,I am getting following error:

"Costing data may not be up to date Display Help

Rollback: Account assignment must be reset "

I have defined costing model and costing variant for ECP.

Please help me solving this error.

Thanks in advance,

Manoj

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

This problem is solved.

It was because some customizing was missing.

Regards,

Manoj

Former Member
0 Kudos

Hi,

Pls check if the WBS element is "planning element"

Regards

Sejo.

Edited by: Sejo Srambikkal on Jan 12, 2011 5:08 AM

Former Member
0 Kudos

hi

please schedule the project and again you can do the linking of WBS to cprojects. because i think the costs are not updated properly.