on 12-15-2010 5:28 AM
Hi
We nee to set completion of maintenace by TECHO the PM order, but once we TECHO the PM order attached PR (pending ) will be deleted so need to set complete indicator without TECHO the PM Order how to do this. Pls advice.
Regards
Kesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.