12-14-2010 2:49 PM
Hi guru,
I created a purchase order with two items,
Item 1: 500 euro delivery date 14/12/2010
item 2: 1000 euo delivery date 14/12/2011
When I run the report of grant management, I see that the system create a commitment item of 1500 euro in 2010 and not 500 in 2010 / 1000 in 2011. In this way, only the budge
Please, could you help me?
Thanks
Regards
Raffaele
12-15-2010 7:37 AM
Hi, check here Public Sector Management-Funds Management Government-Actual and Commitment Update/Integration-General Settings-Override Update Profile for Valtype 51, how Commitment budget update for you Update profile
12-14-2010 3:59 PM
Hi,
What update profile do you use? Maybe, it's working on the posting date and not on the due date?
Regards,
Eli
12-29-2010 11:14 AM
12-29-2010 11:33 AM
12-29-2010 3:12 PM
Hi ALex,
I have added for the update profile 000500 the value type 51 for the purchase order, but when I create a purchase order, the consumption of the budget is all in the 2010 and not in 2011 too.
Could you help me?
Regards
12-29-2010 3:32 PM
Hi, in img Public Sector Management-Funds Management Government-Actual and Commitment Update/Integration-General Settings-Override Update Profile to set up Delivery date for CommBud. for value 51, then run FMN4N tcode for your PO
12-29-2010 5:14 PM
12-29-2010 10:04 PM
Hi,try simulate the same case in test, I mean create new PO
Edited by: alex ice on Dec 30, 2010 9:31 AM
12-15-2010 7:37 AM
Hi, check here Public Sector Management-Funds Management Government-Actual and Commitment Update/Integration-General Settings-Override Update Profile for Valtype 51, how Commitment budget update for you Update profile
12-15-2010 9:30 AM
Hi,
For Grants Management, please check these notes:
[1148553 - Additional attributes for derivation of time slices|https://service.sap.com/sap/support/notes/1148553]
[1485529 - Add Due Date for Timeslice Override BAdI|https://service.sap.com/sap/support/notes/1485529]
With these notes, you could determine the desired budget timeslice in GM depending on PO due date.
Hope this helps
Kind regards
Mar
12-28-2010 4:05 PM
Hi Mar,
thanks for your answer...
I implemented the notes... now, I have to do something in customizing?
Thanks
Regards
01-03-2011 10:36 AM
Hi Raffaelle, are you using the badi as suggestedin the notes I previously mentioned?
thanks!
Mar