block posting in status TECO

ansar_shaikh2
Contributor
0 Kudos

Dear PS gurus,

Is it possible to block postings of goods movements and hours registrations on projects with status TECO?

Regards,

AHS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Ansar,

Yes it is possible to block this business transaction, through User Status.

Regards,

Ravi

ansar_shaikh2
Contributor
0 Kudos

Yes i can forbidden the transaction in OK02 in user status, but how to block hrs posting?

Can you please elaborate the same.

Regards,

ahs

Former Member
0 Kudos

Hi Ansar,

Is your Hrs posting against WBS element or Network activity?

CAT7 or CAT5?

Regards,

Ravi

ansar_shaikh2
Contributor
0 Kudos

Network Activity

CAT2 hrs booking & then via CATA posting in PS

Regards,

ahs

Former Member
0 Kudos

Dear Ansar,

In that case, Did you try forbiddening the "Actual Activity Allocation" business transaction in the Network activity level for your user status.

Regards

Ravi

Answers (1)

Answers (1)

ansar_shaikh2
Contributor
0 Kudos

actually we are using Z instead of CAT2 for time booking, so in the program itself we can give error message while in TECO status.