Hi Experts,
Below is the situation and the problem-
I have a product M at a plant P and two vendors V1 and V2. Product specific T lanes are built both with V1 and V2 with P. I have put a lock indicator for V2 >P. V1>P is perfectly fine and active. M exists at P, V1 and V2.
When i run the heuristics, receipts are created, but 'source' field is blank.
Why doesn't heuristic show V1 as the source for the purchase requistions?
Any pointer would be helpful.
Regards
Manotosh
Hi,
Check the procurement type for the material at vendor locations.The same should be always external procurement.
Also check the following indicators in t-lane
i.All products indicator in means of transport.
ii.Aggr. plng
iii.Detld plng
etc...
If still not working make the other t-lane active and try and check if the material is flowing through the lane.So that you can check the same setting and try.
Hope this will help.
regards,
kaushik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
I got the reason- P was not assigned to a model at V1.
Now another issue
when I am going to /sapapo/mat > extras>assign model for P @ V1, system gives an 'information' "Product P: Added to 0 models, deleted from 0 models"
Any clue how to come out of this?
SAP Msg number- /SAPAPO/DMMOD002
Regards
Manotosh
Edited by: Manotosh on Dec 15, 2010 8:31 AM
Hi,
Check the location is assigned to the same model or not.
When the msg box come "'information' "Product P: Added to 0 models, deleted from 0 models" you can clck on the "?" marked button on the msg box and you will get the proper reason.This is basically the detailed error screen problem.
regards,
kaushik
Hi,
One simpler way to check if TL is being considered or not is to manually create a PR interactively in the snp planning book. If TL is recoganized, you will get the source location in PR.
As regards, TL, within TL, you can carry out consistency check and take necessary actions.
TL also can be checked if it is in the work area within transaction Supply Chain Engineer (/SAPAPO/SCC07).
Finally, If the other blocked TL is creating some problem, it can be deleted to check.
Regards
Datta
Dear Experts ,
This Thread seems little interesting which is applicable for me to in a way
from my understanding from this thread
we cannot have mutiple Transportation lane , if we have mutilple TL for a product , then we cannot able to see source destiantion in the Product view
Like say i have product view which have two TL
some times i use TL 1 and some timess TL2
how to configure or manage in snp
Thanks & Regards
Raj
Hi,
Check for the Validity, lot size and procurement priority defined in the lanes.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nanda,
Thanx for your reply.
Validity is same for both the T lanes- valid as on date, no lot size maintained and proc priority is same for both the T Lanes. In any case, one T lane is blocked and hence not available. I also tried by activating both the T Lanes, changing the proc priority(V1 --> P with 0 and V2 -->P with 999), but still the same result.
Regards
Manotosh