Is there a way to covert an SNP Planned orders to ECC Prod. orders? Can one switch off the PPDS in APO and still get the MRP/ MPS planning in APO and and convert those SNP planned orders into ECC orders in ECC

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Closed.

Former Member
0 Kudos

Hi Abhi,

When you CIF SNP and PPDS planned orders to ECC system there is no diffrenciation between both of them (Because component specific details for the orders are not captured in ECC). So in ECC system you can convert Planned orders to Process or production orders by switching PPDS off in APO.

In APO system, SNP itself can plan for all the levels (RM,PM,FG,SFG) so no need of doing MRP.So you can switch off PPDS.

MPS functionality is available in ECC and not in APO system.