Hi experts,

'm testing the Time Recording Process for the activities of PS projects, and I have some issues:

1- I assign employees to Work Center using TCode CR02

2- I plan the workforce (employees assigned to work centers) using TCode CMP2

3- Once the project is released, I go to CAT2 transaction. I introduce the employee and a data entry profile (a standard one). I was expecting to get a list of the assigned activities of the employee but is not happening. It's possible?

It's possible to see the real work at the project planning board using this process? Considering that I'm choosing a data entry profile where the receiver is a WBS Element? Would be better using another profile?

Thanks in advanced,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please change your data entry profile. Choose the option of 'work with worklist'. It will show all the activities where the work center where personnel no. is assigned.

Regards,

Mahendra Dighe

fortian
Active Contributor
0 Kudos

The data entry profile I'm using has the "with worklist" option already activated.

I must be missing some other point.

fortian
Active Contributor
0 Kudos

I' approve the working times using Tcode: cats_appr_lite.

And I transfer it to Project system by using CAT5.