Factory calendar issue changing validity date

Former Member
0 Kudos

Hi,

We have come across the OSS note 1532398 and 1529649. It's for our Solution Manager system. We are on SP24 EHP1 and i wanted to know how far up can you go in the validity date? I understand the holiday dates need to be changed first but how far up can i go and which calendar would apply for Solution Manager? My understanding is that becuase we are based in the UK only the UK based calendars would need to be changed or does it depend on which country the user accessing the system is based?

your help would be very much appreciated.

Mani

Accepted Solutions (0)

Answers (1)

Answers (1)

Paul_Babier
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Mani,

If you look at SAP Note 501262 - UK Public Holiday Calendar Settings for 2012

Look at Solution 3

3. You can now -> Goto -> Public Holiday calendar -> Assign th

2013 holiday to the calendars GS/GN/GE.

Change valid from / to definition -> select 'Spring Bank

Holiday - 2013' -> valid from = 2013 -> Save

Valid from 2013 to 20XX on your demand

This would suggest that the validity date can be set to any value in the format 20xx.