My client facing problem during creation of shipment document and shipment cost document at the time of Batch Job
Delivery no 897654: goods issue on 30.11 at 13:22. Shipment on 30.11 (VT01N).
Shipment costs on 1.12 (VI01).
the problem is the shipment document get created on 30.11.2010 but the shipment cost document get created on 1.12.2010
pleas advice.
Hi,
Please check the batch job processing log.
As per my understanding, business requires to generate the Shipment & Shipment cost documents immediatley.
However there is some time between the documents creation time. I dont see any issue in the data or problem in the delivery docs Because system will not generate the shipment docs after 1 or 2 days if there is an issue with the data . There must be problem in the Batch Job.
Analyse the batch jobs and timing of the job process.
Let us know your feedback...
Best Regards,
MKumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.