Hello Everyone,

I am doing SMQ1 testing.

I have two questions as mentioned below.

1) If I have made some changes in material then do I need to run some code or transaction to push this material change in to SRM or system will transfer this material change automatically?

2) How can I check on SRM side that this material change has received or not?

Can somebody explain me this material change transfer in SRM from R3 in detail? We are using extended classic scenario.

Regards,

Khushbu.

Accepted Solutions (1)

Accepted Solutions (1)

former_member560682
Participant
0 Kudos

No Replies?..Need help

laurent_burtaire
Active Contributor
0 Kudos

Hello,

Read article below written by Virender Singh:

[Middleware Configuration and Monitoring for Master Data Transfer from SRM to ECC|http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/309258e9-0da2-2d10-b598-bf27edb56a31?quicklink=index&overridelayout=true]

For delta data exchange, even if object classes MATERIAL and SERVICE_MASTER have their triggering events customizing, you need to populate filter settings in R3AC1 transation for those business objects

Regards.

Laurent.

former_member560682
Participant
0 Kudos

Thanks for the reply Laurent.

I read this document and I used the transaction R3AM1 for replication but the status is comming Running from a long time and the destination system is comming CRM. So is this right? I think the destination system should be SRM.

Khushbu.