Hello all,

I am using a work center hierarchy with 2 levels where I maintain the work center capacities at the lower level and aggregate the capacities in the superior level.

I am using the work center that aggregate the inferior work center capacities for scheduling in the planning board. When I am on the planning board tool I can see that my WC has available capacity.

The problem is when I maintain the duration of work in the work order operation the dispatching raises the following error:

- Order 000000600103 operation 0020: No remaining av. cap. Available in planning period.

Does anyone know what I am missing?

Thanks in advance.

Best regards,

Tiago Magalhaes

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Problem solved.

The problem resided on the work center scheduling formula. I have assigned the formula SAPC00 on other formula and it working fine

Regards,

Tiago

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Note 1944967 has just been created with a description of the most frequent causes for this issue.

Take a look on this note on the link below:

https://support.wdf.sap.corp/sap/support/notes/1944967

BR

Caetano