on 12-06-2010 2:07 PM
Hi,
I have been searching through the archives and found a lot of maybe, but no final ideas.
How do you change a Work Center on a Prod Order?
Anybody has a suggesfull way of doing it?
Thanks
Andy
Hi Glenn
You can change almost anything with that bapi, but not the Work-Center.
Thanks
Andy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Andy,
Try using BAPI_ALM_ORDER_MAINTAIN. The documentation states this BAPI is for maintenance orders, but we have used it to change the bill of materials and other parts of the production order.
Glenn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.