Resource Chart in DS board

Former Member
0 Kudos

Hi,

We are using DS Board (only resource chart), WE need to differenciate the following objects by different colors

1. Planned order

2. Production orders - released

3. Production order - created

Can someone post a step by step guide for this.

Cheers,

SM

Accepted Solutions (0)

Answers (1)

Answers (1)

frank_horlacher
Employee
Employee
0 Kudos

Hi,

I cannot give you a complete step by step guide today.

The color of the operations of the orders you mentioned can be changed in the graphical objects of the Detailed Scheduling Planning Board Profile.

1. To carry out the activity, choose one of the following navigation options:

SAP SCM Menu Advanced Planning and Optimization® Production Planning  Environment  Current Settings  Maintain Detailed Scheduling Planning Board Profiles

Transaction /SAPAPO/CDPSC2

2. Select the profile SAP001 and choose Copy asu2026

3. Make the following entry:

PlanBoardProf Short description

DS001 DS Planning Board Profile

4. Choose Enter.

5. In the Specify Object to be copied dialog box, select copy all.

6. Confirm the information dialog box u201CNumber of dependent entries copied:u2026u201D

7. Choose Save.

8. Enter a customizing request.

9. Choose Save and go back.

10. Select the profile you have created before (e.g. DS001) and double-click on the Chart folder in the Dialog Structure section.

Example:

for graphical objects

Graphical Objects Chart

46. Select your profile again and double-click on the Graphical Objects folder in the Dialog Structure section.

47. Double-click on the object OPR_DEF_1 - Operation (Texts in Graphical Objects) .

48. Choose Field Selection and add one of the Product fields by moving it from the right table to the left.

49. Choose Continue.

50. Choose Save.

51. Enter a customizing request.

52. Choose Save and exit the maintenance of the planning board profile.