on 12-04-2010 7:24 AM
Hi,
I have a project for which I have to assign different Status Profile for Different WBS, for example,
WBS 1
WBS 1.1 Sts Prof : X001
WBS 1.2 Sts Prof : X002
WBS 1.3 Sts Prof : X003
WBS 2
WBS 2.1 Sts Prof : X004
WBS 2.2 Sts Prof : X005
I am creating this project using Standard WBS.
Can I by any chance default the Status Profile to the WBS so that when I create Project I get a Project as desired above.
Thanks in advance,
Stephen
HI,
This is standard.
While creating / editing the standard / operative WBSE, you can select whatever the status profile you want.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.