Hi Experts,
I would like to ask you what are the main implications of assigning employees to the project using "Project Team for WBS element" instead of assigning them directly to the Work Centers?
Thanks
Project team assigned to WBS element is available for use in all the work center of activities under this WBS. While if you assign a resouce to work center it is automatically available for project team if you want so.
While when you assign people to work center, then resource planning and capacity levelling is at more microlevel (network activity level).
The workcenter-personnel number is more rigid assignment than assigning a project team to WBS element.
There might be some more points which can have difference in both the process. I expect otherw will also express their views about them.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.