Cannot change project hierarchy after budgeting

Former Member
0 Kudos

Can any one please help with this. I am trying to change the hierarchy of my project but since the project has been budgeted for and released, I get the message that I cannot change project hierarchy. I have tried reseting the budget but this doesn't seem to be working. Any ideas on how I can accomplish this?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

You can try the following procedures:

1. Clear all the budget into 0 ( both overall budget and annual budget)

2. Run t-code OPSX to reset the "BUDG" flag.

3. Try to update your project hierarchy again.

Hope it works.