on 12-03-2010 12:12 PM
Hi,
I have problems understanding who the scheduling works.
I'm using Strict bottom-up as planning method and I've selected network assignment for WBS element.
When I created the project I introduce the Finish date on PD and the duration of the activities. Once I schedule the project everything seems right.
I was trying changing the finish date on de PD and rescheduling all the project but it has no effect, finish date is going back to the original date I had introduced the first time.
My question is which should be the correct procedure to change the finish date and reschedule all the activities? Must I change the finish date on the header network and Project definition?
Thanks in advanced
Try this method:
1) First enter the desired finish date in PD, remove the calcuated start date
2) in gantt chart, select all WBS elements, and delete all dates/duration
3) Now select all objects(including WBS and activities) and reschedule now.
The new dates should be calculated for all objects.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Mahendra,
Very helpful answer!
I would have preferred an easy way (as the one you told me) of doing it from the project builder instead than from the planning board. But it's fine!
I conclude that my mistake was that I wasn't deleting the calculate dates/duration from the WBS
Regards,
mforman
Edited by: mforman on Dec 3, 2010 2:49 PM