on 12-02-2010 10:38 PM
Hi,
We have set up Block Planning for SNP 7.0 and in the runs we are having a new error message:
The Production Process mode l cannot be executed from bucket 20101129->20110102 to bucket 20101129->20110102 because the upper limit for the number of executable lots was set to 0
We have no optimization bound profile, no lot size definition in the PDS and have a simple active planning horizon in weeks.
Any ideas?
Kr,
GWMS
Hi,
Check whether your demand falls with in the SNP Production horizon . If this is the case you will get this error.
Thanks,
nandha