on 12-01-2010 11:37 AM
Hi Experts,
Wanted to check, in configuration of Plant Maintenance ( Specially on Work Order ) where factory calendar need to declare, or its global declaration only, if so How I can find that which calendar is assigned to Plant maintenance object ( interested in work Order )
Thanks in advance
Riyaj
1.Plant calendar
Customizing > Enterprise Structure > Definition > Logistics - General > Define, copy, delete, check plant > Define Plant
You can find 'Factory calendar' for each plant.
2.Work center calendar
Transaction IR03 > 'Capacities' tab > 'Capacity' button
You can find 'Factory calendar ID' for each work center.
3.Maintenance plan calendar
Transaction IP03 > 'Maintenance plan scheduling parameter' tab
You can find 'Factory calendar' for each maintenance plan.
Regards
Luke
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Riyaj
Read the documentation on user-exit IWO10022 via TCode SMOD. This may help..
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.