Scheduling date problem

Former Member
0 Kudos

Dear Experts,

In WBS element dates tab , when i enter basic date as 01.12.2010 and duration as 10 days then instead of 10.12.2010 as finish date system shows 14.12.2010 as finish date. That means system is not taking sat-sun during this entry.

So please guide me where setting is made to take 5 working days instead of 7.

Raghav

Accepted Solutions (1)

Accepted Solutions (1)

former_member203098
Active Contributor
0 Kudos

in oy05 change to 5 working days

regards

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

First check in your project/WBSE what is the calendar you have maintained? and then make the changes for that calendar alone as suggested by Nag.

Former Member
0 Kudos

Dear Experts,

Thanks...i made the setting....

kalpesh_agrawal
Participant
0 Kudos

Change factory calander setting