on 12-01-2010 10:31 AM
Dear Experts,
In WBS element dates tab , when i enter basic date as 01.12.2010 and duration as 10 days then instead of 10.12.2010 as finish date system shows 14.12.2010 as finish date. That means system is not taking sat-sun during this entry.
So please guide me where setting is made to take 5 working days instead of 7.
Raghav
in oy05 change to 5 working days
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
First check in your project/WBSE what is the calendar you have maintained? and then make the changes for that calendar alone as suggested by Nag.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Change factory calander setting
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.