cancel
Showing results for 
Search instead for 
Did you mean: 

Planned total not show even running CJEN ancd CJBN

0 Kudos

Dear expert,

Please help me on this.

I have set up the project, wbs elements, budget amount and release amount in the system. Some PM work orders have been assigned with the WBS element. But somehow in CJ33, there is no planned total existed for WBS elements. I have run CJEN and CJBN to recontruct infor database and availability control, but the problem still unresolved.

Is there any step I missed out in order to get the planned total updated in CJ31/33? I even checked on report in CJE0, it has the detail amount for budget, actual, plan column. But no subtotal in WBS element for 'PLAN--year'.

Thanks in advance.

Best regards,

FLL

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Activate the Appended field in OPSV (check box)for order category 30 .

Muzamil

0 Kudos

Hi Muzamil,

That works. Thank you very much.

regards,

FLL

Answers (0)