on 11-30-2010 7:51 PM
I have installed OpenPSMSP4 to interface MS Project 2007 SP2 with SAP Project System ECC 6.0. However the upload button is deactivated so i cannot transfer from MS Project to the SAP System.
I have already created the role (SAP_PS_EPS) in PFCG and carried out the user maintenance in SU01 along with authorization for object S_RFC and S_USER_GRP but still the button remains deactivated.
Kindly let me know if I need do something else in SAP.
Regards
Salim
Hi,
Try MS Project 2007 SP1 instead of SP2.
This should solve the problem.
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Salim,
upgrade your front-end GUI patch level. This may help to overcome the problem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.