on 11-30-2010 5:12 PM
Hi Experts,
We need new elements created in cProjects 4.5 to be created by default with a specific type. We saw that through user settings we can specify the default type for each user. But, is there any way that we can specify the user settings as part of the user creation?
In this [thread|; there is an answer that involves development.
Is there any procedure that can be executed without development?
Thanks a lot.
Neil
Hi Neil,
You can default this in PFCG role.
Choose the best cProjects PFCG role (maybe a global one, so that all users are affected), and go to "Personalization" tab.
Then, double click on DPR_USER_SETTINGS.
You can now default some parameters, including the default task type.
BR
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
7 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.