on 11-30-2010 11:38 AM
Dear Experts,
While creating project CJ20N, when we assign materials under internal activity and when we release that activity, respective PR's and Reservation nos are generated.
My need is I have solution by which before releasing activity PR and reservation nos should not generate.
please guide.
Raghav
Dear Sir,
I know about L and N . but my question is PR and Resv no. will generate directly or we have to release the activity ??
If they generate before releasing the activity what setting shud I do so that PR and Resr nos won't generate before releasing ?
Thanks
Raghav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can control the creation of PR whether it is immediately or after release..but you cannot control creation of reservation number...whenever you assign material component to activity the reservation number will get generated. For restricting PR generation look for res/pr indicator in network profile.
Hi,
For stock items(L), a reservation will create and for non-stock items only a PR will be created.Check the settings in OPUU the settings for Res./Purc. req.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.