on 11-30-2010 12:07 AM
Hi all,
We are on SRM 5.0 ECS.
When does the COMPLETE button in PO screen gets actiavted ?For some PO's ,This button is always disabled(No badi has been implemented yet) while for some PO's this button is ACTIVE only in the CHANGE mode.
Thanks!
"Complete" button is used to "compensate" PO deletion. When PO deletion is not possible, "Complete" button would be activated. Otherwise, it is not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The Complete button becomes active only in the change mode of P.O and not during P.O creation as there is no question of completing a P.O before creating it.
Once the P.O is created and no follow on documents created, the Delete and Complete buttons both would become active.
And in this case you can either Delete the P.O or Complete the P.O.
But once the confirmation is created for a P.O, the Delete button would get disabled in the P.O change mode and only complete button would be available.
However completing the P.O does not mean that Last Delivery and Final Invoice check boxes have been checked and transfered to ECC.
Though you can not post further confirmations or made P.O changes in SRM, GRs and Invoices can still be created in ECC.
Hope this makes your understanding more clear.
Let us know in case of any further clarifications.
Regards,
Teja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.