RVKRED77 Will it correct Scheduling Agreements?

Former Member
0 Kudos

We have a problem with our deliveries splitting because some of the Scheduling agreements have credit management info on them, and others do not. The scheduling agreements should all have the same credit management info on them. Any idea how to correct this? We want all the scheduling agreements for a given payer to have the same credit management info. We ran RVKRED88 as the simulation and it came up with a list of open deliveries. We have open ended scheduling agreements, we cannot run RVKRED77 every night to correct deliveries. Will RVKRED77 correct the scheduling agreements?

Thank You

Accepted Solutions (0)

Answers (1)

Answers (1)

Shiva_Ram
Active Contributor
0 Kudos

Check whether OSS Note 880557 - RVKRED77 + sched agr w/ rel order: mult value of delvy goods and note 890550 - RVKRED77 + sched agrmnt w/ rel: Mltple value of gds for dely answers your question.

Regards