on 11-29-2010 9:51 AM
Hi experts,
We need to extract the planned order dates and times to an external system. Customer use the external system to create a labor plan for the entire factory.
If I look at R/3:
Planned orders only display start and end basic, no time. Production dates and times fields in the planned order are empty.
Responsible for interfaces wanted to use SAP PI to extract dates and times from R/3 but this is only possible for the process orders.
Could it be better to try extract it from APO? Which is the best way to do this? Note that we are not using BI so standard data sources to extract PPDS data to BW are not considered.
Thanks for your advices.
CTF
Hi,
Always if there is Basic scheduling ( EX SNP Planned Order) only Order start date and Finish date will be populated.
If there is lead time scheduling( Timings from routing is taken for scheduling- Ex PPDS Planned Orders) production dates with times will be populated.
ie you need to carryout lead time scheduling to extract the exact production dates and times from planned Orders.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nandha,
They are PPDS Planned Order, but If I check in the planned order details, I only see the basic dates in the planned order in R/3, no times; I have to check in the PLAF table in order to get the times.
We are planning to extract the data using IDOC LOIPLO01 and LOIPRO01, getting the the material number, order, dates and times from PLAF table and retrieving the resource (missing in PLAF table) from the production version.
Any suggestion? Or is there a better practice?
Thanks
Carlos