Hi,

I would like to know what I should customize in order to change the inquiry status from "A - Not yet processed" to "C - Completely processed" automatically once a quotation has been created in reference to the inquiry.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

In VOV7

Completion rule: [] Not relevant for completion

(It is for quotations and contract items). We can specify that a quotation is complete only after its quantity has been

fully referenced by subsequent document.

Dependencies: In copy control sales document to sales document, check update document flow option at

item category level.

Ex: If the item category for quotations is u201CAGNu201D, then the value will be u201C8u201D.

regards

Prashanth

Answers (4)

Answers (4)

former_member657193
Contributor
0 Kudos

Hi

You can control the completion status of any preceding document throught the "Completion rule in the item category"

--- Status should get completed with first reference

-- status will get completed with complete quantity is fully reference.

Check the relevant item category and set the completion rule to update the required ststus.

Thanks

Rishi.............

Former Member
0 Kudos

hi

this is to inform you that

"A - Not yet processed" to "C - Completely processed" automatically once a quotation has been created in reference to the inquiry.

goto the completion rule in VOV7.

hope this solves your query

balajia.

Former Member
0 Kudos

Pl change completion rule in Item category.

thx

Dilip Sadh

reazuddin_md
Active Contributor
0 Kudos

This feature is std .

Check in VOV7 in item catergory details - field " Completion rule". maintain field accordingly.