on 11-26-2010 3:10 PM
Hi SAP Gurus,
SRM 5.0
Extended Classic Scenario
CCM 2.0
Query : Work Flow triggers the professional purchaser PP in approval previw of SC but there is no email sent to the PP inbox.
No email notification is sent to the Professional purchaser inbox.
Can any one advice on this to locate the error.
Regards,
Jayoti
Very useful and got a hint to resolve my query.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In Function Module RH_LOCAL _INBOX. Check the work item is available in PP approval inbox by inputting PP EMP ID and EN as language.
If the related work item is available, then check in SOST any mail is send to PP from system.
Also verify the program is RSWUWFMLEC is running successfully in the system with right variants if it is scheduled.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
check Attribute forward_wi of PP position is 'X' in the org. structure..
Saravanan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sravanan,
Have gone through the program and when i executed that one , getting the message as -
No work items found that require e-mail forwarding to approver
But I can see at the ITS ( SRM Portal side ) that SC is displaying in approval preview screen - the professional purchasers User ID
And i have also checked in BBP_PD , got the work item ID and cahnecked in Swi1 , when i see the overwiew its not dispaying me any agent there.
Can you please advice.
Many thanks all Specially Sravanan & Laurent
The issue has been resolved now . The problem was RFC Configuration was not setup for workflow in SWU3.
Problem : Email was not triggering in professional purchaser and approver inbox even though we can see I the approval preview screen at the portal
Solution : The work item step was not generating for Agent determination.
In Automatic Workflow Customization ( SWU3 ), Configure RFC Destination under Maintain Runtime Environment was not enabled.
Basis Team ran Perform Automatic Workflow Customizing button situated adjacent to Execute button. And the status for Configure RFC Destination changed from Red cross to Green Tick.
In Automatic Workflow Customization ( SWU3 ) -> Maintain Runtime Environment -> Configure RFC Destination
There were some more options below were in Crossed red status :-
We selected the particular step below and Right Click -> Auto- Customizing
1) Schedule Background Job for Missed Deadlines
2) Schedule Background Job for Work Items with Errors
3) Schedule Background Job for Condition Evaluation
4) Schedule Background Job for Event Queue
5) Schedule Background Job for Event Queue
Regards,
Jayoti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.