AFVC table note updated when Cost element is changed in PR

Former Member
0 Kudos

For External activity PR is created and in PR cost element is changed. When I go back and check the activity in CN22 it reflects new cost element correctly. But when I check the AFVC table entries it still shows the old cost element.

Did any one experienced same problem and I could not find any OSS note on this.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

i haven't come across this problem, however you can check which costelement updated in cooi table. i think

it doesn't matter what costelement updated in afvc table because system concerns more about cooi table for commitments

and reporting.

regards,

Former Member
0 Kudos

I know its not impacting any functionality. But would like to understand the SAP behaviour.

former_member203098
Active Contributor
0 Kudos

i would suggest you to raise this issue to sap