We have around 2000 activities in project. How to identify activities with missing relationship?
in cj20n select the network header and click on the network graphic there on bottom right side you can see the activities
with out relationships.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Oh..I am sorry, I could have executed CN49N thinking that it is CN47N.
I would suggest another way, execute CN41N, you will find all activities but for activities with relationship, you will another row below to that activity showing relationship icon. If the activity is without any relationship then you wont find that row for that particular activity. So you can easily differentiate the activities with relation and without relation easily from this report.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.