on 11-24-2010 12:56 PM
Hi all,
Can you help me? i need to transfer a budget from 2 level WBS of one project to 2 level WBS of anoter project and system allow to do it.
How can i activate budget control not ony 1 level WBS but for 2 level WBS of project?
Best regards,
Dmitry
Hi All,
It is the bad variant. Maybe some body know the way to solve a problem check budjet of WBSE before transfer posting?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Availability is checked against available budget to assigned values, I dont think it will check the budget transfer between WBSE. But it will check whether the input amount is less or equal to available budget of sender WBSE or not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
run txn cjbn for the project, budget availability control gets activated for all the wbse in the project.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes . You can transfer the buget from level 2 WBSE of 1st project to Level 2 WBSE of 2nd project. Go to CJ34. Give Document date , Select the check box Overall values too....then enter...then fill the 2nd level WBSE's & required value & save it.
You can check the transferred budgets in tcode CJ31.
Regards,
Pradip
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.