Item category L is not defined (check entry)

atul_rajmane
Participant
0 Kudos

Hi,

While attaching a material to network with Item Category L, I am getting following error message.

Item category L is not defined (check entry)

Message no. CO131

I am able to attach the material with Item category N, but not with Category L.

Let me know possible reasone for same.

best regards,

Atul Rajmane

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

Goto OS13 and check whether item category 'L' is defined there are not

atul_rajmane
Participant
0 Kudos

Hi,

In OS13, L is maintained with + for tick at PMStr location.

After putting Inventory management indicator on, I am able to add material with L category in Project.

But, every time I am addting material by default its taking Reservation for network. I am not able Select Reservation for WBS or PR + Res for WBS. I have not putting any of Procurment Indicator also.

Kindlly advice the same.

regards

Atul Rajmane

former_member203108
Active Contributor
0 Kudos

Uncheck the PMStr for L category, Also have you maintained project stock indicator at project definition level?

Edited by: Ahmed Rifaee on Nov 24, 2010 5:36 PM

Former Member
0 Kudos

HI

check OPT1 also. if you want the logistics for WBSE then select 221 movement type where relevant.

regards

Former Member
0 Kudos

This also happens if you have not assigned the activity to the WBS element.