on 11-24-2010 8:49 AM
Hello,
Does anyone know how to set job schedule at each month end?
as you all know, for each month, end date is different from month to month.
but we need to execute a job at month end... is there any good method?
thanks advance for your kind reply and advice.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Using SM36/SM37 it is difficult to get this facility. There is another job scheduling tool (Redwood - SAP CPS) which is used to overcome this type of difficulties. You can check Redwood guides in SAP help docs.
Thanks,
Subrata