Demand transfer from ECC to SNC using RSMIPROACT Programme

Former Member
0 Kudos

Hi,

Presently we are using RSMIPROACT to transfer demand (Planned independent Requirements-T-code MD61)from ECC to SNC.

It transfers the demand always from version 02 and not from the active version 00.

I want to know whether there is config to change this.We want to send through 00 verison also.

Thanks and Regards

Raghavendra Pai

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Raghavendra Pai

In ERP system, transaction OMPD. Each transaction has been assigned to active version.

I believe in your case it is version 02 as active.(Guess)

If you want both active version and other version data to be sent, then try to enhance the code in includes available in RSMIPROACT program.

Kindly seek help of PP guy and ABAPER.

Hope this helps, As per my knowledge we have different versions, so that we can simulate long term PIR and differentiate between various planning approaches.

Best Regards

Vinod