Planning ETM Equipment in Project ...

Former Member
0 Kudos

Hello Everybody

I m planning machine hours of ETM (Equipment & Tools Management) equipment in my project. I have done all the necessary settings required and are getting requirement generated automatically in ETM planning board without making requisition note. Planning board is also letting me assign PS requirement to ETM equipment but is not allowing me to create shipping document from planning board. When i press SHIPPING button on planning baord, message appears that " NO RECIPIENT COULD BE DETERMINED" !

Recipient and sender are mentioned in requisition note which i have avoided as i have generated requirement from my PS Project. Can anyone advise if i have to create requisition note for the requirement generated from PS Project as well or i could enter recipient in PS project as well?

I know this question is more related to ETM, but PS Gurus might help me as this is one the requirement of construction industry of EC &O Projects and equipment machine hours are planned in Projects.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Everyone Again

I have found answer myself.

Recipient of ETM Requirement generated from PS Project has to be created through VD01 (Create Customer) with Project Definition as recipient type.

This recipient type allows certain project definition to be entered in customer master data which becomes the recipient while making shipment document of equipments.

former_member203108
Active Contributor
0 Kudos

Thank you for coming back with the solution.

former_member203108
Active Contributor
0 Kudos

If you dont get good response here, then try posting it in IS forum, you may find lucky there.