on 11-23-2010 9:09 AM
Hello,
The requirement is system should create only 3 inspection lots for a material+Vendor.
From 4th time onwards material should go directly for Unrestricted stock
For Inspection type : 01
Is there any configuration to map this ?
Kindly share your views
Thanks
I would suggest you implement DMR (dynamic modification rule) function.
SAP system can create 3 inspection lot with 'REL' status for inspection, then from 4th inspection lot can be created with 'SKIP' status for inspection skip.
The skip inspection lot can be decided usage and posted to unrestricted stock by automatic UD function.
But material is not gone directly to unrestricted, it needs time for background job execution.
Regards
Luke
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear this is for per a day or whenever you do GR for that particular material and vendor combination from 4th time onwards you don't want system to generate inspection lot?
Cheers
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.