Hi All -

The PPM in APO has the setting " Production Within a Shift". Can you please let me know the mapping field on the R/3 side so that I can CIF it? We are using APO 4.1 and ECC 6.0.

Appreciate all your help.

Varun

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I don't think this field comes from R3. But you can maintain thru MASSD Function.

Thanks,

nandha

Former Member
0 Kudos

Hi Nandha,

And if instead of PPMs, we are using PPDS PDSs, is it any possibility to restrict the production within a shift?

We have one shift per day so it would be to restrict production to one day volum as maximum. Planned order should never pass from one day to another.

We are using Max Lot size slightly smaller that max production during a day, setups are in scope, but it does not work so well.

Thanks

Regards

Carlos

Former Member
0 Kudos

Hi guys,

Any comments about this topic? How can we limit production within a shift if we use PDSs instead of PPMs?

Comments will be very appreciated.

Thanks a lot!!!

CTF

Former Member
0 Kudos

Hi guys,

Any comments about this topic? How can we limit production within a shift if we use PDSs instead of PPMs?

Comments will be very appreciated.

Thanks a lot!!!