cancel
Showing results for 
Search instead for 
Did you mean: 

Sourcing in SNC

Former Member
0 Kudos

Typically in SNC Customer Collaboration we have a default source location, that means one single default Transportation Lane.

we need to split the sourcing on 2 different planes like a quotation 25% from Plant A and 75% from Plant B.

This logic is available in APO.

What we would like to develop is a functionality to force the replenishment in SNC before creating planned receipts to read out the valid sourcing via quotations.

So e.g. we have a demand for the ship-to location of 1000, Replenishment should get the information that 250 should be sourced from Plant A and 750 from Plant B.

Based on this planned receipts should be created in SNC Replenishment based on this u2013 also taking into account a rounding.

How to go ahead on this?

Thx

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear VAIBHAV VIRKUD,

For me it is not possible to fix this with standart way...

You have to fix this case by applying customer enhancement.

Cheers.

Former Member
0 Kudos

Hi Vaibhav

Similiar functionality is availabe with in Customer Collaboration.

Replenishment with Dynamic Sourcing..........For this you need to have transportation guidelines, sets and Replenishment Service profile, Alternate source supply etc.

http://help.sap.com/saphelp_scm70/helpdata/en/47/505b1826870a1de10000000a42189d/frameset.htm

Go to Replenishment Planning-Replinishment Service-Sourcing-Dynamic Sourcing

Where you get to meet your demant from differect source of locations, and the corresponding Planned reciepts and TLB orders are created

Best Regards

Vinod