Account assignment in planned order

Former Member
0 Kudos

Hi,

We are using CTM planning and MTO(20) scenario.

Inquiry is made planning relevant After CTM planning run,.planned order gets created with account assignment (E) w.r.t. inquiry.

When I convert the inquiry w.r.t. sales order (using VA01) and then take the planning run, a new planned order gets created but in ECC the account assignment object in the planned order still remains inquiry where as it should be w.r.t. sales order.

In APO the planned order is pegged to sales order and the planning segment is still the inquiry number.

Regards,

Yogesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check in the Strategy definition for 20 in ECC what is the account assignment category is defined.

Thanks,

nandha

Former Member
0 Kudos

Hi,

The accnt assignment category is 'E' - Ind. cust. w. KD-CO.