on 11-16-2010 11:45 AM
Hi Experts,
I would like to ask for your help ow to fix the issue regarding the incorrect dates that is set by the system when creating a planned order.
When I create an order in product view; the availability date that I set was not applied by the system instead it set the date a day before and the time is 24:00:00
Examples:
availabilty date: 21/11/2010 22:00:00
order was set by the system to:
start date: 20/11/2010 00:00:01
end date: 20/11/2010 24:00:00
Thank you and have a nice day!
Regards,
Marlon